Try 2 sample questions
Taken from the free sample set for APM-PFQ.
Question 1
When are benefits usually realised when using an iterative life cycle?
- AOption A:
During the project
- BOption B:
Post project
- COption C:
At project closure
- DOption D:
Both during and after the project
Show answer and explanation
Correct answer: D
Question 2
Risk management should be initiated.
- AOption A:
when the Project Management Plan is initiated.
- BOption B:
at the time the Work Breakdown Structure is developed.
- COption C:
at the start of the project.
- DOption D:
once the project concept is understood.
Show answer and explanation
Correct answer: C