Skip to main content

BIM_MGT_101 Autodesk Certified Professional in BIM Management for Building Design

  • AutoDesk
  • 5 free sample questions

About this exam

BIM_MGT_101 is the AutoDesk exam Autodesk Certified Professional in BIM Management for Building Design. Paid practice material for this exam is not available yet, but you can try its free sample questions.

Exam code
BIM_MGT_101
Vendor
AutoDesk
Practice questions
Not available yet
Free sample questions
5
Question bank last updated
Not available yet

Try 2 sample questions

Taken from the free sample set for BIM_MGT_101.

Question 1

Which of the following would typically be included in an AECO BIM data handover package at project closeout?

  1. Option A:

    Internal meeting notes from model coordination sessions.

  2. Option B:

    Federated design models used during clash detection.

  3. Option C:

    3D views used for clash detection during model coordination.

  4. Option D:

    Record models with the required asset data embedded.

Show answer and explanation

Correct answer: D

A project-closeout handover package should contain verified record models populated with the asset information required by the owner’s operational and facilities-management processes. Depending on the defined information requirements, this may include asset identifiers, classification, manufacturer and model data, installation information, warranty details, maintainability fields, commissioning status, spatial relationships, and links to associated documentation.

The record model must represent the accepted project condition rather than an intermediate coordination state. It should undergo final validation for required parameters, naming, file format, model structure, and information completeness before delivery. Where COBie or another structured asset-data format is required, the embedded model information should correspond with the exported dataset.

Federated clash-detection models and temporary 3D coordination views are process artifacts. They may be archived where the contract or organizational retention policy requires them, but they are not normally the principal operational deliverable. Internal coordination notes likewise document project activity but do not provide the owner with a usable digital representation of the completed facility.

The defining characteristic of a BIM handover deliverable is verified, structured information that supports the owner’s specified post-project uses.

Reference topics: BIM closeout; record models; asset-information requirements; COBie; facilities-management handover; data validation; digital deliverables.

===============

Question 2 (choose 2)

The BIM manager has finalized the BIM Execution Plan (BEP) for a multi-discipline educational facility project. Some consultants have already

begun modelling, while others are onboarding late. A few external stakeholders are not listed in the original BEP distribution but

will need access to coordinated models during design and preconstruction.

What two actions could be taken in order to manage distribution of updates? (Select two.)

  1. Option A:

    Update and reissue the BEP only to the consultants who have not yet started modelling to ensure they catch up to

    project standards.

  2. Option B:

    Formally distribute the BEP to all relevant parties as an addendum to the contract.

  3. Option C:

    Formally distribute the BEP to all relevant parties and confirm receipt to ensure alignment on roles,

    responsibilities, and agreed BIM processes.

  4. Option D:

    Upload the BEP in a shared Autodesk Forma Data Management folder to ensure version tracking and verify

    access to stakeholders.

  5. Option E:

    Wait until construction coordination begins before sharing the BEP with external stakeholders.

Show answer and explanation

Correct answer: C, D

The revised BEP must be distributed to every party whose work or information access is governed by it, including consultants already modelling, late-onboarding participants, and relevant external stakeholders. Formal distribution with confirmation of receipt establishes that each organization has received the current requirements and understands its modelling scope, coordination obligations, information exchanges, approval responsibilities, and communication procedures.

The controlled copy should also be stored in the project’s Common Data Environment. Uploading it to the shared data-management location provides centralized access, version history, revision traceability, and a consistent source of truth. The BIM manager must verify that each stakeholder has appropriate folder permissions rather than assuming that uploading the document automatically makes it accessible.

Issuing the BEP only to newly onboarded consultants would leave existing participants working under obsolete requirements. A contractual addendum may be required when the revision changes contractual obligations, but it is not automatically the correct mechanism for routine distribution management. Delaying access until construction coordination would undermine design-stage coordination and prevent external stakeholders from following the approved procedures.

Reference topics: BEP distribution; document control; Common Data Environment; version management; stakeholder access; receipt confirmation; project onboarding.

===============