Skip to main content

CIS-PPM ServiceNow Certified Implementation Specialist - Project Portfolio Management

  • Servicenow
  • 5 free sample questions

About this exam

CIS-PPM is the Servicenow exam ServiceNow Certified Implementation Specialist - Project Portfolio Management. Paid practice material for this exam is not available yet, but you can try its free sample questions.

Exam code
CIS-PPM
Vendor
Servicenow
Practice questions
Not available yet
Free sample questions
5
Question bank last updated
Not available yet

Try 2 sample questions

Taken from the free sample set for CIS-PPM.

Question 1

A customer requires five (5) teamspaces to support different departments. What should you do?

  1. Option A:
    Enable the teamspace property.
  2. Option B:
    Contact the Account Representative to activate the teamspaces.
  3. Option C:
    Activate via each teamspace plugin.
  4. Option D:
    Use UI Policies and Business Rules to enable teamspaces.
Show answer and explanation

Correct answer: C

In ServiceNow, Teamspaces are enabled through specific plugins, and each teamspace functionality is activated via its corresponding plugin rather than a single global property or manual configuration. Since the customer needs multiple teamspaces for different departments, the correct approach is to activate the required teamspace plugins, which then allows those spaces to be configured and used independently for each department.

Question 2

When creating a resource plan within a demand, how are the default dates on a resource plan determined?

  1. Option A:
    From demand start date and due date
  2. Option B:
    Resource plan(s) cannot be created from demand
  3. Option C:
    Using demand created date
  4. Option D:
    From portfolio date a is right
Show answer and explanation

Correct answer: A

When a resource plan is created from a demand in ServiceNow, the system automatically sets the default planning window using the Demand Start Date and Demand Due Date. These dates define the expected timeframe for the work, so the resource plan inherits them to ensure alignment between demand scheduling and resource allocation. This helps in accurately planning capacity and staffing based on the demand lifecycle.