Skip to main content

AgilePM-Foundation Agile Project Management (AgilePM) Foundation Exam

  • APMG-International
  • 150 practice questions
  • Updated Aug 2026
  • 5 free sample questions

About this exam

AgilePM-Foundation is the APMG-International exam Agile Project Management (AgilePM) Foundation Exam. Practice material is available as a PDF, an interactive practice test or a bundle of both.

Exam code
AgilePM-Foundation
Vendor
APMG-International
Practice questions
150
Questions with an explanation
0 of 150
Free sample questions
5
Question bank last updated
11 Aug 2026

Try 2 sample questions

Taken from the free sample set for AgilePM-Foundation.

Question 1

During what phase should the strategy for Iterative Development be considered?

  1. Option A:
    Pre-Project
  2. Option B:
    Feasibility
  3. Option C:
    Foundations
  4. Option D:
    Evolutionary Development
Show answer and explanation

Correct answer: C

The strategy for Iterative Development should be considered during the Foundations phase. This phase establishes a firm foundation for the project, ensuring that only the right projects are started and that they are set up correctly, considering aspects such as feasibility and business case1. It’s crucial to have a clear strategy for Iterative Development at this stage to guide the subsequent phases of the project effectively. 

Question 2

Which statement about DSDM roles is true?

  1. Option A:
    In DSDM, one person must hold several roles
  2. Option B:
    One DSDM roles does NOT necessarily mean one person
  3. Option C:
    All DSDM roles should be shared
  4. Option D:
    DSDM roles should NOT be split between two people
Show answer and explanation

Correct answer: B

In DSDM, it is true that one DSDM role does not necessarily mean one person. This allows for flexibility in assigning roles based on the project’s needs and the individuals’ skills and capacities. It is possible for one person to hold multiple roles or for a role to be shared among several people, depending on what is most effective for the project. 

See all 5 free sample questions