Try 2 sample questions

Taken from the free sample set for PMP.

Question 1

The vendor just informed the project manager that an item will not be delivered as scheduled due to a manufacturing error. This will impact the delivery timeline of the

project as there are dependencies to the completion of this item delivery.

What action should the project manager take?

  1. Option A:

    Contact the vendor and insist on the agreed timeline since any item delay will affect the overall project.

  2. Option B:

    Agree with the vendor on a revised timeline, document the issue, and identify tasks to finish while awaiting delivery.

  3. Option C:

    Ensure this is documented as an issue and wait until the vendor delivers the item before progressing with any further tasks.

  4. Option D:

    Ensure that the vendor is removed from the vendor management list to avoid working with them in the future.

Show answer and explanation

Correct answer: B

The correct answer is B because the scenario requires disciplined procurement and supplier management rather than an immediate, informal, or purely administrative reaction. The selected response — B. Agree with the vendor on a revised timeline, document the issue, and identify tasks to finish while awaiting delivery. — directly addresses the condition described in the question and keeps the project aligned with authorized objectives. PMBOK-aligned practice requires the project manager to assess supplier capability, contract impact, cost, quality, schedule, and available alternatives before committing project resources. This is especially important when project constraints, stakeholder expectations, quality expectations, delivery cadence, or business value may be affected. The competing options are weaker because they either bypass the accountable role, defer action without analysis, escalate before the project manager has prepared decision-quality information, or solve a symptom without correcting the underlying process issue. The selected answer also preserves transparency, ownership, and traceability, which are essential for sound project governance and effective delivery. PMBOK® Guide Eighth Edition topics: process, procurement and supplier management, stakeholder communication, impact analysis, governance, value delivery, and continuous improvement.

Question 2

Asubject matter expert (SME) working for the client ' s company is coming up with new project requirements periodically. This causes confusion, time is wasted

rearranging the requirements. The project manager has learned that this SME is a new to the project.

What should the project manager do?

  1. Option A:

    Gather the project imperatives from historical project documents.

  2. Option B:

    Update the change management plan with the new requirements.

  3. Option C:

    Review baselined requirements with the SME.

  4. Option D:

    Escalate the issue with the SME and project sponsor.

Show answer and explanation

Correct answer: C

The correct answer is C because the scenario requires disciplined stakeholder engagement rather than an immediate, informal, or purely administrative reaction. The selected response — C. Review baselined requirements with the SME. — directly addresses the condition described in the question and keeps the project aligned with authorized objectives. PMBOK-aligned practice requires the project manager to clarify expectations, preserve transparency, and use the appropriate decision or communication channel. This is especially important when project constraints, stakeholder expectations, quality expectations, delivery cadence, or business value may be affected. The competing options are weaker because they either bypass the accountable role, defer action without analysis, escalate before the project manager has prepared decision-quality information, or solve a symptom without correcting the underlying process issue. The selected answer also preserves transparency, ownership, and traceability, which are essential for sound project governance and effective delivery. PMBOK® Guide Eighth Edition topics: process, stakeholder engagement, stakeholder communication, impact analysis, governance, value delivery, and continuous improvement.